Code: Select all
MasterTestSuite
SoftwarePackage
TestA
TestB
TestC
......
TestFinal
Here's why:
Currently if TestA or any other 1 child test fails, my report will show that 3 tests failed ( TestA, SoftwarePackage, and MasterTestSuite ) which is incorrect since SoftwarePackage and MasterTestSuite aren't actual tests. So my question is, can I change the settings somewhere to turn this feature off? I'd like SoftwarePackage and MasterTestSuite to NOT report a pass/fail state since they are only being used for data providing purposes.
Also is it possible to attach two csv data connectors to one test case? Or do they have to be nested as I am doing? Is there a way to attach a csv file at the TestSuite level (it only allows me to add Global Parameters)?